Kitchen Remodeling in Houston, TX

Kitchen remodeling Houston homeowners plan in 2027, with each kitchen renovation Houston TX scope priced:

All kitchen scopes

$15,000–$85,000

Same layout: new cabinets, quartz, tile5–7 weeks after cabinets arrive

$26,000–$48,000

Prices are Henry Remodeling estimates for Houston-metro projects in 2027. Last reviewed November 2026. Sources and method

Get Instant Quote

A rough planner by room size. The pricing tables on this page are the published Henry Remodeling 2027 estimates.

Step 1 of 3: project details
Approximate room size

A midrange major kitchen remodel in Houston averaged $81,521 and recovered 46.8% of its cost at resale in Zonda’s 2025 Cost vs Value Report.

A major Houston kitchen remodel recovers less than half its cost at resale, so Henry Remodeling shows owners the same-layout option beside the full redesign before they commit to moving walls or plumbing.

Henry Remodeling
Galley kitchen with white shaker cabinets, a navy island with wooden stools and wood-look plank floors

Quick Answers: Kitchen Remodeling in Houston

What does a kitchen renovation Houston TX homeowners book include?

A kitchen remodel in Houston includes demolition, new cabinets, countertops, backsplash, flooring and trim, plus any sink, appliance or lighting changes. Henry Remodeling installs the casework, stone, tile and floor; relocated plumbing, new circuits and wall removal go through our GC partners and their permits.

Kitchen remodeling Houston: what does it cost in 2027?

Houston kitchen remodeling runs from $15,000 for a cabinet-and-counter refresh in a compact kitchen up to $85,000 for a large kitchen with semi-custom casework, a new island and layout changes. The common middle is $26,000–$48,000 for new plywood stock cabinets, quartz, tile backsplash and porcelain or LVP in the same footprint.

Why does a Houston kitchen need a different spec?

A Houston kitchen remodel needs a different spec because the slab under it rises and falls with the Beaumont clay, which opens countertop seams and racks long cabinet runs. Humid air swells particleboard as well, so we install level-first in plywood boxes and test the slab for moisture before any flooring goes down.

What Our Houston Kitchen Remodels Include

A kitchen renovation Houston TX homeowners plan starts with the floor plan you want and the slab you actually have. We open each project with a moisture reading, a laser level across every wall that will carry cabinets, and a look at what the old sink base says about past leaks. The scope below is what a standard Henry Remodeling kitchen covers; layout changes are added through our GC partners.

Henry Remodeling provides specialized, hands-on installation services working under the umbrella of established General Contractors. While our dedicated craftsmen deliver flawless tile, cabinetry, and surface installations, our GC partners pull all required city or county permits and coordinate the state-licensed plumbing and electrical trades along with the structural scope.

  • Laser-level survey of every cabinet wall and island location, with the high point of the slab marked as the install datum
  • Moisture test of the slab where the new floor and base cabinets will sit, with results written into the scope
  • Tear-out of cabinets, tops, backsplash and flooring, with disposal and protection of the rooms around the kitchen
  • Plywood-box base and wall cabinets, shimmed to the datum and screwed to studs and to each other
  • Countertop templating after the bases are set, with seams placed off the sink and cooktop and supported underneath
  • Tile backsplash on a primed substrate with flexible sealant at the countertop joint instead of grout
  • Porcelain tile on an uncoupling membrane, or rigid-core LVP over a vapor-retarding underlayment
  • Final trim and hardware, appliances set back in place with water, drain and power reconnected by GC partner trades, and a punch walk before the last invoice

Kitchen Remodel Scopes Compared

Houston kitchen projects sort into four scopes. The difference is how much of the existing room stays.

TypeBest forHouston noteTypical price
Surface refresh: refacing or new doors, new tops and backsplashSound boxes and a layout that worksOnly if the sink base reads dry; tops still need a level check$15,000–$26,000
Same-layout replacement1990s–2000s builder kitchens with swollen bases or dated stonePlywood boxes and level-first install replace particleboard set on a moving slab$26,000–$48,000
Replacement with island or minor layout changeOpening a peninsula, adding an island sink or moving the rangeNew circuits and drain runs go through the GC partner’s permits$42,000–$65,000
Full redesign, semi-custom or custom caseworkLarge kitchens in high-value neighborhoods or older homes being opened upWall removal and floor-plan changes need a city permit inside Houston or Katy limits; elsewhere the GC partner confirms what the county, Township or HOA requires$60,000–$85,000

Benefits of a Kitchen Built for Houston Conditions

Countertop seams that stay closed

Stone set on bases that were shimmed to a single datum carries the slab’s seasonal movement evenly, so seams and the sink cutout are not pried open each August.

A sink base made for small leaks

Plywood holds its shape and its screws when the trap drips or the dishwasher hose weeps. Particleboard in the same spot swells once water reaches it and loses its hold on the screws.

Floors that suit a slab with a history

Testing the concrete first means the right adhesive or underlayment is chosen before the floor goes down, so tile stays stuck down and LVP stays flat.

Layout changes on one schedule

Moving the sink or adding island power goes to the GC partner’s plumbing and electrical trades, with permits where the property’s jurisdiction requires them, inside the same schedule, so you are not coordinating two crews.

How Much Does Kitchen Remodeling Cost in Houston?

In 2027 a Houston kitchen remodel runs $15,000 to $85,000. Cabinet line and box material, countertop square footage, flooring area and any layout change set the number; slab work is listed separately so it does not hide inside the total.

ScopeTypical Range (Houston Metro, 2027)
Refresh: refaced or new doors, quartz tops, tile backsplash (compact kitchen)$15,000–$26,000
Same layout: plywood stock cabinets, quartz, backsplash, LVP or porcelain$26,000–$48,000
Island added or sink and range moved (permitted work through GC partners)$42,000–$65,000
Large kitchen, semi-custom or custom casework, wall removed$60,000–$85,000
Add-on: slab moisture mitigation and leveler under a 200 sq ft kitchen floor$1,200–$3,300

Thumbtack’s July 2026 Houston data puts typical kitchen remodels at $7,592–$26,089, a range that overlaps our $15,000–$26,000 refresh; our same-layout and larger scopes run above it because each one replaces the cabinets in plywood and adds new tops. Block Renovation’s review of 729 Houston kitchen permits averages $36,841, which falls inside our $26,000–$48,000 same-layout band. ContractorPlus puts a 100 sq ft Houston kitchen at $21,383–$42,765, built on about 120 labor hours at $123.27 an hour across demolition, cabinets, appliances, flooring and finishing. Its range starts inside our refresh band and ends inside our same-layout band. Our refresh can start lower because it keeps sound cabinet boxes and skips the demolition and new casework that estimate includes.

Houston metro pricing as of November 2026. You receive an itemized estimate, and nothing is ordered until it is signed.

What Changes the Price of a Houston Kitchen Remodel

We built these numbers per linear foot of cabinet, per square foot of countertop, backsplash and floor, and per appliance or fixture reset, then added 2027 Houston installer hours for each item. Leveling, moisture mitigation and any permitted trade work are separate lines. The resulting totals were checked against Thumbtack, Block Renovation and ContractorPlus figures for Houston.

Cost driverWhen it appliesAdds to the job
Casework grade and box materialEvery replacement scopeStock plywood roughly $260–$340 per linear foot installed; semi-custom $340–$480; custom $520–$650+
Countertop material and square footageAll scopesQuartz or granite about $60–$110 per sq ft installed; a 50 sq ft kitchen $3,000–$5,500
IslandNew island or island replacement$4,000–$12,000 before any plumbing or power
Backsplash tileStandard 30–40 sq ft wall area$1,200–$3,500 depending on tile and pattern
Flooring and underlaymentPorcelain on membrane or LVP on vapor retarder, 150–250 sq ft$2,500–$7,000
Base leveling on a moving slabOut-of-level runs over about 1/4 in in 10 ft$200–$600 per run
Permitted plumbing and electrical via GC partnersSink move, island sink, new circuits, under-cabinet lighting$2,000–$9,000
Wall removal via GC partnersOpening to the family room; may need a beam$3,500–$12,000

Kitchen Costs in Houston Versus the Nation

National Baseline vs. Houston

Block Renovation reports the Houston kitchen average at $36,841 against $46,623 nationally and $45,545 across Texas, roughly 21% under the U.S. figure. Its labor table shows cabinet makers and finish carpenters at $85–$110 an hour here. Lower land and labor costs explain most of the gap.

What the Houston Spec Adds to the Price

Much of the extra cost in a correctly built Houston kitchen goes into things nobody sees after install day: plywood boxes where particleboard would be cheaper, shims and screws at every base joint, a membrane under tile and a moisture test before the floor. Skipping them can trim a bid by several thousand dollars. The cheaper bid leaves stone on unlevel bases and particleboard at the sink, which is how countertop seams open and sink bases go soft.

Block Renovation, Houston kitchens

$36,841

Average of 729 local permits, about 21% below the U.S. figure

Typical Houston range (Thumbtack)

$7,592–$26,089

July 2026 Houston data

100 sq ft kitchen (ContractorPlus)

$21,383–$42,765

Houston estimate, November 2026

Kitchen Remodeling Price by Area in Houston

Kitchen size and the casework buyers expect drive area differences. Estimates below run from a cabinet refresh to a full custom rebuild, depending on the area, and are listed from the most expensive area downward. Inside any one ZIP code, the kitchen scope still sets the final figure.

Area (ZIP)What drives the price thereTypical range
Houston: Memorial 77024Top-tier city market; larger kitchens, custom rebuilds and stone throughout$50,000–$85,000
Spring: Gleannloch Farms 77379Golf master plan at the top of the Spring market; larger kitchens trading up$34,000–$60,000
Shadow Creek Ranch 77584, PearlandOne of Pearland’s top-priced areas; 2000s kitchens with builder particleboard$32,000–$50,000
Coles Crossing 77433, CypressMid-market Cypress; 1998–2008 homes on very reactive clay$26,000–$44,000
Bear Branch Village 77339, KingwoodMid-priced Kingwood; 1970s–90s original kitchens$25,000–$44,000
West Lea 77584, PearlandLower-priced 1980s stock; original finishes$19,000–$32,000

Kitchen Remodeling Budget Tiers in Houston

Each budget level below uses the same installation standard. What changes is how much of the kitchen is replaced and the casework grade.

Low Budget

$15,000–$26,000

Keep sound boxes, reface or replace doors, add quartz tops and a tile backsplash. Floor stays unless it is failing.

Mid-Range

$26,000–$48,000

New plywood stock cabinets on leveled bases, quartz or granite, tile backsplash and a new floor over a tested slab, same layout.

High-End

$42,000–$85,000

Semi-custom or custom casework, an island with sink or power, layout or wall changes through GC partners, premium stone and tile.

Late Surprises, Thin Bids and Kitchen DIY

Hidden Kitchen Remodeling Costs Not in Most Houston Quotes

  • Rotten subfloor or damp slab under the sink: years of small leaks often show up only when the base comes out. Drying, treating or patching adds $600–$2,000.
  • Flooring that runs under the old cabinets: many 1990s kitchens have tile that stops at the toe kick. A new layout exposes the gap, and the floor has to be replaced wall to wall.
  • Undersized circuits for modern appliances: an induction range or a second oven may need a new dedicated circuit, which is permitted work through the GC partner.
  • Drywall repair after tear-out: old backsplash and upper cabinets usually leave torn paper and anchors behind. Plan $400–$1,200 for patch and texture.

Why Cheap Quotes Fail in Houston

  • Particleboard boxes across the whole kitchen, including the sink base
  • Cabinets set to follow the floor with no level line, leaving stone to bridge low spots
  • Countertop seams placed at the sink or cooktop cutout, the weakest point in the slab
  • New LVP clicked over a slab nobody tested, under cabinets that will be hard to remove later

DIY Kitchen Remodeling Risks in Houston

  • Setting a long run of bases dead level on a slab that is out by half an inch takes a laser, shims and a fixed datum
  • Stone fabricators template from the installed bases; a DIY base that moves after templating can crack the top
  • Moving the sink or adding outlets goes to the GC partner’s plumbing and electrical trades; inside Houston city limits it also needs a permit, and elsewhere the GC partner confirms what the city, county or HOA requires
  • Heavy wall cabinets on a single row of screws into drywall anchors are a known failure; they must hit studs

Houston-Specific Kitchen Factors

Insider tip

Find the slab’s high point before a single cabinet is set. Shoot a laser line around every wall that will carry base cabinets and the island footprint, mark the highest spot, and set all bases to that datum with composite shims at every stile. On Beaumont clay a 20 ft run is often 3/8 in to 5/8 in out, and a top laid on bases that follow the floor will put a stone seam in tension the first time the slab settles in a dry summer. Leveling to the high point means the shims only ever get thicker, never thinner.

5 Houston Factors That Shape Every Kitchen Remodeling Project

Clay and long cabinet runs

A 20 ft run of cabinets spans enough slab to feel seasonal heave and settlement. Shimming each base to one datum and tying cabinets together lets the run move as one piece instead of opening at joints.

Humidity and casework

Dew points in the low 70s mean the inside of a sink base rarely dries out completely. Plywood boxes and sealed edges at the sink and dishwasher hold up in that.

Flood history and the kitchen floor

Kitchens near Brays Bayou, Clear Creek, Cypress Creek, Lake Houston or the reservoirs often sit on slabs that took water in 2017 or 2019. A moisture test decides the floor build before cabinets cover it.

Permits follow the layout

Houston city rules exempt cabinet, countertop and tile work; replacing or moving the sink and any electrical work need permits. Suburban cities, county areas and HOAs such as Bridgeland, Cinco Ranch and Sienna add their own steps.

Heat and stone near the range

A quartz top beside a high-output range or a Houston summer window still needs trivets and shade; granite tolerates heat better. We review range placement before choosing the top.

When Is a Full Kitchen Remodel the Right Scope?

  • Several boxes besides the sink base are soft or swollen
  • You want a different layout: an island, an open wall to the family room or a relocated sink
  • Countertops, backsplash and floor all date from the original build and would each need replacing within a few years
  • The kitchen took on water in a flood and the casework has to come out anyway
  • You are preparing a long-term home and want one disruption instead of three
  • Not the right scope: dry, sound boxes in a layout you like. Cabinet refacing plus new countertops costs far less

Illustrative Transformation: Kitchen Remodeling in Houston

An illustrative Houston kitchen from tear-out to handover, assembled from typical scopes; no particular client’s home is shown.

Before: the Starting Kitchen Remodeling Scope

A 2002 suburban kitchen with 24 particleboard cabinets, a granite top with an open seam at the sink, and builder tile that stops at the toe kicks. The sink base floor is soft, the dishwasher-side cabinet has swollen at the bottom edge, and a laser shows the back wall run is 1/2 in lower at one end.

After: the Finished Kitchen Remodeling Scope

The slab tests dry enough for tile. Bases are set to the high point on composite shims, all in plywood, with a new island where the peninsula was. The GC partner’s plumber and electrician handle the island sink and outlets, under permit where the city requires one. Quartz is templated after leveling, with seams kept off the cutouts. Porcelain plank runs wall to wall on an uncoupling membrane, and a ceramic backsplash finishes the walls. Roughly nine weeks on site.

What Sets Henry Remodeling Apart: Kitchen Remodeling in Houston

Level Before Stone

Every base run is set to a single laser datum and fastened before the fabricator is called, so stone seams stay closed when Houston slabs shift.

Plywood Where Water Lives

Sink, dishwasher and wet-wall cabinets are plywood boxes in every replacement scope. A refresh keeps the existing boxes only when the sink base reads dry.

Moisture Results in Writing

Slab readings are recorded in the estimate so you can see why a floor build or mitigation primer was chosen.

Permits and Trades Through GC Partners

Henry Remodeling provides specialized, hands-on installation services working under the umbrella of established General Contractors. While our dedicated craftsmen deliver flawless tile, cabinetry, and surface installations, our GC partners pull all required city or county permits and coordinate the state-licensed plumbing and electrical trades along with the structural scope.

A Kitchen Planned Around Lead Times

A temporary sink station and refrigerator spot are planned on day one, and the schedule is built around cabinet and stone lead times so the room is not left open waiting.

Our Kitchen Remodeling Process

A Houston kitchen job moves through seven steps, and the slab survey comes before any cabinet order.

StepWhat happensTypical time
1. Site surveyLaser level of all cabinet walls, slab moisture reading, sink-base and subfloor check, jurisdiction confirmed by address1–2 hours
2. Design and estimateLayout, cabinet line, top, backsplash and floor chosen; GC partner scopes any permitted work; itemized estimate signed1–3 weeks
3. Ordering and permitsCabinets ordered; permits filed by the GC partner where required; HOA notice sent2–6 weeks
4. Tear-out and rough-inOld kitchen removed, slab prepped or mitigated, plumbing and electrical roughed in by the GC partner’s trades, under permit where required3–7 days
5. Floor and cabinetsFloor installed where it runs under cabinets; bases set to datum, uppers hung, island anchored4–8 days
6. Countertops and backsplashTemplate after leveling, fabrication, install; backsplash tiled and sealed at the top joint2–3 weeks including fabrication
7. Finish and handoverHardware, trim, appliances set in place (GC partner trades reconnect them), punch list and walkthrough2–4 days

Common Problems We Solve: Kitchen Remodeling in Houston

Open seam at the sink

Stone set on a base run that followed a sagging slab. The tops come off, the bases are re-shimmed to a datum, and a new top is templated with the seam moved away from the cutout.

Soft, swollen sink base

Particleboard that absorbed leaks for years. The whole run is replaced in plywood and the leak source is routed to the GC partner’s plumber.

Doors that drift out of line every summer

The cabinets were fastened to the floor and never tied to each other at a level line. New runs are tied together and leveled so they move as a unit.

Cracked tile across the kitchen floor

Rigid tile bonded straight to a slab with a shrinkage crack. The crack is treated and new porcelain goes down on an uncoupling membrane.

What Can Go Wrong: Kitchen Remodeling in Houston

Six ways a Houston kitchen remodel can fail are listed below, each with its cause and the step that lowers the risk.

ProblemCause and prevention
Quartz cracking near the cooktopA seam or narrow strip near the cutout, on a base that was never leveled, is under constant stress. Leveling first and placing seams away from cutouts takes that stress off the stone.
Cabinets pulling off the wallUppers hung into drywall anchors loosen as the house moves. Every upper is screwed into studs through a hanging rail.
Floor bubbling under the refrigeratorGlue-down flooring on a damp slab releases. A moisture test and the correct adhesive or a floating floor over a vapor retarder avoid it.
Backsplash cracking at the countertop lineGrout where tile meets stone cracks as the top and wall move differently. A flexible sealant joint there absorbs the movement.
Dishwasher leaks into a new baseA hose clamp missed at reinstallation can ruin a new cabinet. The GC partner’s plumber makes the water and drain connections, and the dishwasher runs a full cycle with the base open before sign-off.
Project stalls waiting for stoneOrdering tops before bases are set adds a second template trip. Templating right after leveling keeps the schedule tight.

Common Mistakes and Homeowner Checklist: Kitchen Remodeling in Houston

6 Common Contractor Mistakes in Houston Kitchen Remodeling

  • Letting the floor set the cabinet height: the stone ends up bridging every low spot in the slab
  • Choosing particleboard to save on the sink base: the cheapest box in the kitchen is the one most likely to get wet
  • Ordering the countertop from plans: fabricators need a template from installed, leveled bases
  • Skipping the moisture test because the slab looks dry: concrete can read dry on top and still be releasing moisture
  • Grouting the backsplash to the countertop: the joint cracks the first time the slab moves
  • Planning an island without checking jurisdiction: a new island sink or circuit needs a permit inside Houston city limits, while for unincorporated county and Woodlands addresses the GC partner checks the county, Township and HOA rules first

Kitchen Remodeling Pre-Project Checklist for Houston Homeowners

  • Ask how base cabinets will be leveled and whether a single datum is used
  • Confirm the box material at the sink, dishwasher and every wet wall
  • Ask for the slab moisture reading and what floor build it leads to
  • Confirm countertops are templated after bases are set and fastened
  • Ask where seams will fall and how they are supported
  • Find out who files permits for sink moves, island power or wall removal
  • Check HOA rules for dumpsters, deliveries and work hours
  • Plan where you will cook and wash dishes during the work

How Long Does Kitchen Remodeling Take in Houston?

Best Case

3–4 weeks

Refresh scope: new doors or refacing, tops and backsplash on a level, dry kitchen.

Typical

5–7 weeks

Same-layout replacement with new cabinets, stone, backsplash and floor.

Extended

8–12 weeks

Islands, layout changes, wall removal or semi-custom cabinet lead times.

What Causes Timeline Extensions in Houston

  • Waiting on casework: Stock lines ship in roughly 1–3 weeks; semi-custom and custom take considerably longer.
  • Stone fabrication: Most fabricators need 1–2 weeks after templating, and templating waits for leveled bases.
  • Permit review: Sink moves, new circuits or wall removal wait on city review wherever the jurisdiction requires a permit, and the GC partner files it.
  • Slab mitigation cure time: A mitigation primer or leveler needs to cure before flooring and cabinets go on it.

Representative Project Scenarios: Kitchen Remodeling in Houston

The three kitchens below are illustrative composites drawn from typical Houston scopes, written to show how neighborhood and jurisdiction shape the work. They are not completed Henry Remodeling projects; every figure is an estimate.

Ranch Kitchen Opened to the Family Room: Memorial 77024, Houston

Client Profile: Owners of a 1960s ranch who plan to stay put and open up its closed galley kitchen.

Key Challenge: Removing the wall between kitchen and den means a beam and relocated circuits, both permitted. The 1960s slab has a long settlement crack under the old dining area that is treated before porcelain goes down on a membrane. Semi-custom plywood cabinets and a quartzite top.

Location Context: City of Houston; the Houston Permitting Center reviews the wall removal and the electrical and plumbing changes, filed by our GC partner. Cabinets and countertops themselves are permit-exempt. Deed restrictions may apply.

Investment Range: $68,000–$80,000  Timeline: 10–12 weeks on site

Builder-Grade Kitchen Upgrade: Shadow Creek Ranch 77584, Pearland

Client Profile: A family in a mid-2000s home with a 26-cabinet kitchen, swollen sink base and a granite seam that has opened.

Key Challenge: Expansive clay has dropped the corner of the slab under the sink wall about 1/2 in. Bases are set to the high point, all in plywood; the existing island stays in place with new tops. LVP goes over a vapor-retarding underlayment after testing.

Location Context: City of Pearland Permits and Inspections Division; the city requires permits for remodeling, repairs and MEP work, so the GC partner applies through the city’s CityWorks system before work starts. HOA rules in the master plan also apply.

Investment Range: $38,000–$48,000  Timeline: 5–6 weeks on site

Island Added to a Golf-Course Home: Gleannloch Farms 77379, Spring

Client Profile: Owners of a 2000s home replacing a peninsula with a working island.

Key Challenge: Sandier soil means the slab is closer to level than on the west side, but the island sink needs a new drain and vent and a dedicated circuit. Plywood stock cabinets, quartz with an overhang supported by steel brackets, and a full-height backsplash.

Location Context: Unincorporated Harris County, so there is no county building permit for the cabinets or tops; the island plumbing and electrical go to the GC partner’s trades, and the GC partner confirms what the county requires. HOA and deed restrictions in the master plan also apply.

Investment Range: $46,000–$60,000  Timeline: 8–10 weeks on site

Difficulty Factors: Kitchen Remodeling in Houston

A Gulf Coast kitchen takes more care to install than one on rock or in a dry climate.

Long runs on a moving base

A kitchen spans more slab than any other room’s casework, so it sees more of the clay’s movement. Datum leveling and tied runs keep it in check.

Stone is unforgiving

Quartz and granite do not flex. Any unevenness in the bases becomes stress in the stone, usually at a seam or cutout.

Wet zones in a humid house

The sink, dishwasher and refrigerator line all add water to air that is already damp. Box material and sealed edges matter more here than in dry markets.

Different floors under the same house

Some older Houston kitchens sit on pier-and-beam or on additions with a different slab, and the floor build has to change at the joint.

Who Needs Kitchen Remodeling in Houston

Four Houston households that plan kitchen remodels, and the work their homes need:

HouseholdHomes and typical work
Owners of 1940s–70s ranches inside the BeltwayKitchens in Oak Forest 77018 and Memorial 77024 that were closed off and never updated, often with original slabs that need crack treatment.
Families in 2000s–2010s master-planned homesOwners in Southern Trails 77584 and Telfair 77479 replacing builder particleboard with plywood and stone.
Owners rebuilding after a floodKitchens in Kings Point 77345 and Forest Bend 77546 where the base cabinets took water and the slab needs testing before anything goes back.
Long-term owners in north-side communitiesHomes in Champion Forest 77379 and Northpointe 77377 where long-term owners are replacing original kitchens.

Materials & Methods: Kitchen Remodeling in Houston

Six components decide how a Houston kitchen performs after the first few summers.

ComponentSpecificationWhy it holds up on Houston clay and in Houston humidity
Box construction3/4 in plywood sides, backs and floors; at minimum at the sink, dishwasher and wet wallsHolds shape and fasteners in humid air and after small leaks
Leveling and fasteningComposite shims to a laser datum at every stile; cabinets screwed to studs and to each otherLets the run move as one unit with the slab
CountertopsQuartz or granite templated from installed bases; seams off cutouts, supported underneathEven support keeps stone from cracking as the slab moves
BacksplashCeramic or porcelain on primed drywall; flexible sealant at the countertop jointThe soft joint absorbs movement where two different surfaces meet
FlooringPorcelain on an uncoupling membrane, or rigid-core LVP on a vapor-retarding underlaymentHandles slab cracks and residual moisture
Sink base protectionWater-resistant liner or sealed plywood floor in the sink cabinetSmall drips do not reach the box material

Cities We Serve for Kitchen Remodeling

Kitchens in every city we serve get the same level-first install, but the slab, the flood history and the permit office change.

Each city page below covers that community’s permit office, soil, flood history and neighborhoods for kitchen remodeling work.

Sources, Methodology & Page Review: Kitchen Remodeling in Houston

Our kitchen prices are Henry Remodeling estimates for 2027 Houston installs. We priced cabinets per linear foot by grade, stone and tile per square foot, and appliance and fixture resets per item, then added local labor and listed slab work and permitted trade work separately. We compared the totals with the outside data below. Neighborhood, soil, flood and permit details come from our fifteen-city Houston research file.

Sources Used for Kitchen Remodeling in Houston

  1. Block Renovation: Kitchen renovation costs in Houston, TX
    Permit-based average ($36,841), Texas and national comparison and Houston trade labor rates
  2. Thumbtack: Houston kitchen remodel cost guide
    Typical Houston range ($7,592–$26,089) from July 2026 data
  3. ContractorPlus: Kitchen remodel cost in Houston, TX
    100 sq ft kitchen estimate ($21,383–$42,765) and phase-hour breakdown
  4. Houston Permitting Center: Residential storm damage repair permit guidelines (rev. May 2024)
    Cabinets and countertops exempt; sinks, plumbing and all electrical work need permits
  5. Schluter Systems: DITRA uncoupling membrane
    Uncoupling under kitchen floor tile to neutralize substrate movement
  6. Zonda: 2025 Cost vs Value Report, Houston
    Houston midrange major kitchen: $81,521 job cost, $38,166 resale value, 46.8% recouped

Last reviewed: November 2026. Figures, permit details and benchmarks are rechecked every spring and fall, or right away if one of these sources changes its numbers.

Frequently Asked Questions: Kitchen Remodeling in Houston

How much does kitchen remodeling in Houston cost in 2027?

Kitchen remodeling in Houston costs $15,000–$85,000 in 2027. A refresh with refaced or new doors, quartz and backsplash starts near $15,000; most same-layout replacements with plywood cabinets, stone, backsplash and a new floor cost $26,000–$48,000; islands, layout changes and custom casework reach $85,000. Slab mitigation under the floor adds $1,200–$3,300.

Kitchen remodeling Houston permits: when do I need one?

Inside City of Houston limits, replacing kitchen cabinets, countertops and tile is permit-exempt finish work. Replacing, moving or adding a sink, any electrical work and removing a wall require permits, and suburban cities, unincorporated county areas and HOAs each have their own process. Henry Remodeling provides specialized, hands-on installation services working under the umbrella of established General Contractors. While our dedicated craftsmen deliver flawless tile, cabinetry, and surface installations, our GC partners pull all required city or county permits and coordinate the state-licensed plumbing and electrical trades along with the structural scope. See our city-by-city permit guide for each office.

What should I do with a kitchen that flooded?

A flooded Houston kitchen needs its wet base cabinets, drywall and insulation removed, then the slab dried and tested before rebuilding. Plywood cabinets, porcelain or rigid-core floors and a tested slab are the standard for the rebuild. City of Houston flood repairs need a permit. Our flood rebuild guide for kitchens and baths walks through the order of work.

Why do granite and quartz countertops crack in Houston kitchens?

Granite and quartz countertops in Houston kitchens usually crack because the cabinets under them were set to a slab that later moved. Stone does not flex, so it cracks at the weakest point, often a seam or the sink cutout. Leveling bases to a single datum before templating, and placing seams away from cutouts, prevents most of it.

Is plywood worth it over particleboard for Houston kitchen cabinets?

Yes, plywood is worth it for Houston kitchen cabinets, at least at the sink, dishwasher and any wet wall. Particleboard swells permanently when it gets wet, and Houston humidity keeps sink bases damp. Plywood holds its shape and its screws far longer for a modest premium.

Kitchen renovation Houston TX: how long does it usually take?

On a Houston kitchen renovation, refresh scopes take 3–4 weeks on site, same-layout replacements 5–7 weeks, and kitchens with islands, wall removal or semi-custom casework 8–12 weeks. Cabinet lead time, stone fabrication and any permit review set most of the calendar.

Can I add an island to my Houston kitchen?

A Houston kitchen can usually take an island if there is about 42 in of clearance on working sides. A dry island needs only cabinets and a top; an island with a sink or outlets needs new drain, vent and circuits from the GC partner’s trades. Inside City of Houston limits that work needs a permit. Outside city limits, including The Woodlands, the GC partner confirms the county, Township or HOA requirements for the address.

What flooring works best in a Houston kitchen on a slab?

The best floors for a Houston kitchen on a slab are porcelain tile on an uncoupling membrane or rigid-core LVP over a vapor-retarding underlayment. Both tolerate humidity and slab moisture better than laminate or solid wood, and the right choice depends on the moisture test result.

Summary: Kitchen Remodeling in Houston

Service

Kitchen remodeling Houston homes: plywood cabinets, countertops, backsplash and flooring, with layout changes through GC partners

Cost Range

$15,000–$85,000 (most same-layout kitchens $26,000–$48,000); slab mitigation $1,200–$3,300 extra

Timeline

3–4 weeks for refreshes, 5–7 weeks same-layout, 8–12 weeks with islands or wall changes

Material Note

Plywood boxes, quartz or granite templated after leveling, sealant joint at the backsplash, porcelain on membrane or LVP on vapor retarder

Houston-Specific

Laser datum leveling for clay-driven slab movement and moisture testing before floors; the core of any kitchen renovation Houston TX homes need

Service Area

Greater Houston: the city, Bellaire and Kingwood; Katy, Cypress, Sugar Land and Missouri City to the west; The Woodlands, Spring, Tomball and Humble to the north; Pearland, Friendswood, League City and Pasadena to the south and east

Related: Cabinet replacement, Countertop installation, Backsplash installation, Kitchen flooring installation, Kitchen flooring cost, Houston permit guide, Flood rebuild guide, Cabinet refacing vs. replacement

Get an Instant Quote for Kitchen Remodeling in Houston

Send us the kitchen you have and the one you want. We will level-survey the slab, test it, and price every line before a single cabinet is ordered. Call (346) 537-8290 or request a free estimate online.